Inspections are meant to be made within what timeframe?

  1. 24 hours

  2. 48 hours

  3. 3 days

  4. 5 days

The correct answer is: 48 hours

Inspections in the context of the Washington Administrative Code (WAC) are generally required to be performed within a set timeframe to ensure timely compliance with electrical safety standards. The correct answer indicates that inspections should take place within 48 hours, which aligns with the regulatory intent to maintain a balanced approach between the timely review of electrical work and allowing sufficient time for scheduling and execution of inspections. This timeframe ensures that any issues can be identified and rectified swiftly, thus promoting safety and compliance in electrical installations. The 48-hour window reflects a practical approach to managing workload while prioritizing public safety.