Within how many days must repairs to corrections be made?

  1. 10 days

  2. 15 days

  3. 30 days

  4. 90 days

The correct answer is: 15 days

Repairs or corrections to electrical work that do not meet code requirements must typically be made within 15 days. This timeframe is established to ensure that any safety or compliance issues are addressed promptly, minimizing risks and maintaining adherence to safety standards outlined in the Washington Administrative Code (WAC) and Revised Code of Washington (RCW). Prompt corrections also help ensure that projects progress as scheduled and do not incur additional costs or complications related to delays. Choosing 15 days acknowledges the importance of timely resolution to uphold electrical safety and quality.